As part of the Potomac Interceptor (PI) Sewer Restoration Project, this consists of the rehabilitation of the existing E-line Sanitary Sewer at Washington Dulles International Airport. The line conveys roughly 60 million gallons per day of wastewater from Washington Dulles International Airport and local communities to the Potomac Pumping Station in Washington D.C.
Close coordination with airport personnel is required throughout all active work performed. To minimize disruption, work is being conducted in eight carefully planned stages.
Need
The PI was constructed in the 1960s, and, if not renewed, extensive RCP deterioration could result in environmental damage. Rehabilitation methods will avoid, minimize, and mitigate potential environmental impacts from the restoration efforts.
‘Work
Dulles, VA
Water
Bid-Build
2026
Metropolitan Washington Airports Authority
East